For customers
already owning their own land, Fritz provides
consultation
and
estimating
services to help identify your property’s unique
characteristics and features, and translating this information
into an accurate land improvement estimate.
Our estimates consider the following
items in calculating your total land improvement costs:
LOT CLEARING: Any trees, stumps and
brush removal.
WELL: Cost determined by depth of
well, gallons of water per minute and size of holding tank
and pump.
SEPTIC SYSTEM: Cost determined by
perk test, number of bedrooms, and type of soil.
SUMP LINES: Determined by the lay
of the land or catch basin, when applicable.
GAS LINES: Cost determined by distance
from road or from gas main.
ELECTRICAL LINES: Cost determined
by distance for power lines or pedestal.
ENGINEERED SITE PLAN: Municipalities
requirements - As builts, house staking and building permit
when applicable.
CULVERT: Size determined by Road Commission
and when needed.
CONSTRUCTION DRIVEWAY: Cost determined
by footprint. Crushed concrete base and depth of finish
covering is determined by soil conditions.
FINISHED DRIVEWAY 21-AA: Finish coat
on drive unless concrete, asphalt, etc. is used.
CONCRETE APRON: Cost determined by
size of garage, lay of land, and sidewalk as needed by
Building Code.
FILL SAND: Cost determined on elevation
of home. All garages, porches and aprons must be filled
with sand.
FILL DIRT: Additional dirt required
other than dirt from basement.
LOT BALANCING: Final grading of lot.
Bulldozer time.
DAYLIGHT BASEMENT: Determined by grades,
septic permit and lay of land.
WALKOUT BASEMENT: Determined by grades,
septic permit and lay of land.
FINAL GRADE: Determined by septic
field or grade of land.
|